Heading: 1.2Concrete roping during trowel finishing
Message:
I would appreciate any suggestions. We are experiencing some problems with our concrete "roping" during finishing. We have no air entrainment. The concrete is poured on plastic both inside and outside pours. It occurs when the trowel machine goes one way the length of the slab and then turns to come back. A ridge is created with the paste(cement/sand) and it is difficult to level/flatten out. What can be done by the finisher and is there anything that the ready mix plant can do with mix to reduce/eliminate problem. I have been told that tilting the blades will help. Now blades are being kept flat. We have tried changing our mix several times and still have problem. We are using limestone but have also tried a blended creek rock/limestone mix. Any suggestions would be appreciated. We continue to get great breaks with our concrete. Our sand may have some gap grading and some extra sand on the 50/100 seive. Our sand is natural sand not manufactured.


---------------------------------------------
Sarah Wittenauer


Hi Sarah

May be should try to reduce the paste in your mix (cement +sand).

A too rich mix in paste can lead to such problems.

Rgds

Vikram
---------------------------------------------
Vikram Gunnoo
 
   Click Here to Reply    Areas
Advertise Here