New Humber hospital features innovative concrete

(Canada) — An aggressive schedule, a targeted 30 per cent recycled content in the cement and massive concrete pours including a continuous 13-hour one are just some of the construction dynamics of the 1.6-million-square-foot Humber River Regional Hospital.

Located on an infill site directly across from the Ontario Ministry of Transportation headquarters on Keele Street in Toronto, the approximately 200-metre-long complex is comprised of a 15-storey tower and two six-storey podiums.

The most innovative feature of the concrete structure is the lack of construction joints, says Kathryn Edwards, associate with Halsall Associates, the structural consultant and member of the Plenary Health Care Partnerships, the private consortium which is developing the $1.75-billion acute care hospital under a 30-year concession agreement with the province.

“Buildings as long as this one would typically have expansion joints or pour gaps to allow shrinkage of the concrete.”

Instead, the engineers and builders have implemented a system of temporary contraction joints which will be left in the floor structure to allow the shrinkage of the concrete to occur over several months after which the joints will be connected to complete the floor diaphragm.

The podium is separated into nine slab areas and the tower into three slab areas which eliminated “the need for costly expansion joint hardware.”

There are also a number of other design and construction features which distinguish the hospital from other similar large-scale projects, she says.

A case in point is the use of two different foundations systems – a raft slab for the tower and 5,500-mm-wide strip footings for the podiums.

The raft slab was chosen because the bedrock below the tower is more than 30 metres below the basement elevation. As for the wide-strip footings, they are only supporting six storeys “as opposed to the tower which is 15 storeys tall and therefore heavier.”

The size of the hospital and speed of construction are also notable, says Edwards, pointing out that all of the concrete will be poured in a short 14-month period, from May of this year to June 2013.

For PCL Constructors Canada Inc., the construction arm of Plenary Health, the combination of the size, speed and design have required and are requiring major logistical planning and co-ordination with its subtrades and concrete supplier Innocon.

From the last week of March to early May, the company organized three massive concrete pours of approximately 4,000 cubic metres each to build the 180-metre-long, 40 metre-wide and 1.8-metre-deep raft slab under the tower footprint. The longest lasted 13 hours, says general superintendent Dean Xuereb.

Managing those pours was not difficult, but it did require an early Saturday morning starting time and that, in turn, meant that municipal approvals had to be obtained, and trucks, manpower, and other services had to be in place. Eighty trucks from four different plants delivered the concrete.

“It started with a 3 a.m. debriefing of all PCL staff to ensure placing and materials managers were ready. Constant radio communication was vital but in most cases for the three pours we met all our objectives.”

The challenges continue, Xuereb says.

With eight tower cranes and four placing booms on site, there is constant co-ordination to ensure there is always enough concrete.

Approximately 2,500 to 3,000 cubic metres are trucked to the site weekly.

“We advise Innocon weekly of our expectations.”

Approximately 400 workers are on site, but that figure will most likely increase to 1,200 when the project hits its peak at the beginning of 2014, says Xuereb.

Construction started last fall and is expected to take until 2015 to complete.

By: Dan O’Reilly
Source: http://dcnonl.com/article/id52246/–new-humber-hospital-features-innovative-concrete

(Visited 113 times, 1 visits today)

Get involved

Register

As a member of this site you will be able to receive aggregates news relating only to those categories that are most relevant to you, submit job listings for FREE, post questions in the Q&A, and more.

Register Now

Feature your company

The Feature Your Company listing is your custom-made (by us) profile page that allows you to add any of the following content: text, videos, links, images. The page will also be listed on the Featured Company landing page. Over 560 unique aggregates users visit the site per day! Complete the enquiry form now to contact us.

Contact us

Jobs

Are you looking for an aggregate related job? Click here to see our jobs listing supplied by industry experts United Employment.

See Jobs

Advertise

Reach thousands of budget holders and decision makers by promoting your company on the longest established aggregate website in the US & Canada. Or advertise in our emails which are sent to opted-in subscribers according to their chosen categories. All advertising will display correctly on tablets and mobiles as this site is responsive.